planning time fence
Hi friends
I have define a Item A in inv with planning time fence control user defined with 20 days , let us consider today date is ( jun 14 2012) there is a demand for the item on ( jun 24 2012 ) , there is no on handqty for this item .
According to the oracle document its clear that for the item in the planning time fence , plannning will not resudule in or create planned orders . But how the planning can meet that demand .
Please reply asap.
Thanks in advance
Oracle 'll show an expection
Oracle 'll show an expection message .
Now its the job of the planner
Planner can manually create a supply for it or 'll change the date of the demand...
System 'll just show this as an exception
Hi
Thankyou very much for the
Hi
Thankyou very much for the response ..
please , can u direct to any link to understand the
planning process with a business scenario example .
I have went through the documents but i feel better
still more if i look the concepts with a business scenario
example
pls share any link or related stuff
Thanks in advance.
shivam
Seach MRP in youtube, you ‘ll
Seach MRP in youtube, you ‘ll find many videos explaining the complete process in details…
Pick up any good book on basic of supply chain management like Tony Arnold or Vollman
Hi,
As per my knowledge,ASCP
Hi,
As per my knowledge,ASCP engine will reschdule out the supplies even if it lies within the planning time fence...
Try out test cases to confirm it.
Thanks
That’s correct it 'll suggest
That’s correct it 'll suggest reschedule out but it won’t suggest reschedule in within planning time fence